Fair 35°

BikeCar

DDOT Projects Update: Nov. 13-26, 2017

The District Department of Transportation (DDOT) plans to work on the following alley, sidewalk and road-paving projects in the next two weeks.

Road Paving Projects

Blair Road NW Pavement Restoration Project: Monday, November 13, through Friday, November 17

Paving and restoration will occur on Blair Road NW from Monday, November 13, to Friday, November 17. DDOT will mill and pave at the intersection of Blair Road NW and Kansas Avenue NW from Monday, November 13, to Friday, November 17. DDOT will also conduct saw-cutting and sheet patching at the intersection of Blair Road NW and Kansas Avenue NW from Thursday, November 16, to Friday, November 17.

Eastern Avenue NE Pavement Restoration Project: Monday, November 13, through Friday, November 17

DDOT will adjust a sewer manhole on Eastern Avenue NE, from Sheriff Road NE to Addison St NE, from Monday, November 13, to Wednesday, November 15. DDOT will mill and pave on Eastern Avenue NE, from Nannie Helen Borroughs NE to Kenilworth Avenue NE, from Thursday, November 16, to Friday, November 17.

19th Street NW Pavement Restoration Project: Monday, November 13, through Friday, November 17

Sidewalk restoration will occur on 19th Street NW from Monday, November 13, to Friday, November 17. DDOT will restore sidewalks, driveways, curbs, gutters and ADA ramps between DuPont Circle NW and M Street NW.

M Street NW Pavement Restoration Project: Monday, November 13, through Friday, November 17

Sidewalk restoration will occur on M Street NW from Monday, November 13, to Friday, November 17. DDOT will restore sidewalks, driveways, curbs, gutters and ADA ramps between 22nd Street NW and New Hampshire Avenue NW.

Citywide Sidewalk Restoration Projects

As part of DDOT’s commitment to improve and restore local sidewalks, work will be conducted at the following locations throughout the following two weeks, weather permitting:

  • Cathedral Avenue NW, between 29th Street and Connecticut Avenue);
  • E Street NW, between 18th Street and 19th Street;
  • Quackenbos Street NW, between 2nd Street and 3rd Street;
  • Blaine Street NE, between 47th Street and 49th Street;
  • Piney Branch Road NW, between Whittier Street and Van Buren Street;
  • Blaine Street NE, between 55th Street and 56th Street;
  • Park Road NW, between 11th Street and 13th Street;
  • Clay Street NE, between Division Avenue and 53rd Street;
  • Ames Street NE, between 49th Place and 50th Street;
  • 55th Street NE, between Foote Street and Nannie Helen Burroughs Avenue;
  • 49th Place NE, between Fitch Place and Foote Street;
  • Ames Street NE, between 35th Street and 36th Street;
  • B Street SE, between 34th Street and the dead end;
  • Texas Avenue SE, between E Street and F Street;
  • Livingston Road SE, between 3rd Street and Atlantic Street;
  • Suitland Road SE, between Alabama Avenue and Southern Avenue; and
  • Hanna Place SE, between Benning Road and 51st Street.

Alley Improvement Projects

DDOT will conduct alley improvement at the following locations. The projects will include concrete alley paving starting Monday, November 13. Once work begins, access to parts of the alley under construction will be closed, and parking will not be available. In emergency situations, access may be permitted by notifying DDOT. Work is estimated to take about two weeks, weather permitting.

  • Square 0431 bound by D Street NW, 7th Street NW, E Street NW and 8th Street NW;
  • Square 0196 bound by Massachusetts Avenue NW, 15th Street NW, M Street NW and 16th Street NW;
  • Square 1876 bound by 38th Street NW, Ingomar Street NW, Connecticut Avenue NW and Huntington Street NW;
  • Square 1867 bound by Chevy Chase Parkway NW, McKinley Street NW, Connecticut Avenue NW and Morrison Street NW; and
  • Square 2274 bound by 30th Place NW, Ellicott Street NW, Linnean Avenue NW and Garrison Street NW.

Related articles

  1. DDOT Projects Update: Nov. 6-19, 2017

    Ongoing major construction projects include the pavement restoration projects on Blair Road NW and Eastern Avenue NE.

    Read More
  2. DDOT Lane Closure at Blair Road, Kansas Avenue NW Intersection Starting Thursday

    Vehicular traffic will be prohibited on weekdays at 9 a.m.-4 p.m. and on Saturday at 7 a.m.-7 p.m.

    Read More
  3. Parking prohibited during nightlife hours Thursday, Friday and Saturday.

    DDOT Debuts Temporary Nightlife Parking Prohibitions on Connecticut Avenue This Weekend

    DDOT “parking demonstration” will prohibit parking from 10 p.m. to 7 a.m. Thursday, Friday and Saturday on Connecticut Avenue NW from Rhode Island to DuPont Circle.

    Read More
  4. 49th Street between Fulton and Dexter closed for repairs.

    DDOT Temporarily Closes 49th Street in Northwest for Repairs

    Work is expected to take 3-4 months.​